Free Newsletter


Sign up for our free Enews!!!



Pick Your Location Journal Documentary Get Involved About


Articles

Strike Three... The Corps Fails Again to Justify the Delaware River Deepening
by Dick Bewick, Dave Keifer, and Mike Casale
Sierra Club - Delaware Chapter

In June 2002, The U.S. General Accounting Office (GAO) released a report evaluating the U.S. Army Corps of Engineers' ("the Corps'") proposal to deepen the main navigation channel of the Delaware River from 40 to 45 feet. Based on that report, GAO determined that the actual benefit cost rate (BCR) for this project was approximately 0.5. Since projects are only economically justified if the BCR is greater than 1.0, this finding called into question any previous conclusions to proceed with the project.

The Corps' response was not unexpected. Instead of accepting the GAO's findings and terminating all further work on study and design, it conducted its own "economic reanalysis" and concluded that the project was justified after all. Its BCR was not high (1.14), but not surprisingly, it was high enough to meet the minimum requirements for construction. In December 2002, the Corps released its "Comprehensive Economic Reanalysis Report for the Delaware River Main Channel Deepening Project (Pennsylvania, New Jersey and Delaware)", as well as supporting documents.

What did the Corps do during the six-month period from June to December 2002 to "save the project?"

•It changed its analysis and forecast for crude oil imports, by far the most important commodity affected by the channel deepening.

• It found new commodities, where service has been recently initiated, and extrapolated current market conditions over the 50-year project life.

• It re-estimated the amount of dredge material that needed to be removed, now concluding that less dredged material than previously estimated would need to be removed and disposed of.

• It reevaluated the likely cost of acquiring land for dredge spoil disposal, reducing this cost estimate.

• It used a project discount rate that was significantly lower than in past studies, thereby dramatically altering project cost projections.

• It continued to ignore outstanding environmental issues, including compliance with applicable environmental laws, which could dramatically impact project costs. In response to GAO recommendation, the Corps introduced a new study process for the Reanalysis, ostensibly to provide a clearer picture of how the Corps reached its conclusions. "Independent" Review Boards were established using "out-side" consultants. (Though questions have been raised about the true independence of these Corps-hired consultants.) The reviewers raised serious questions addressed separately by the Corps. While the documents provided by the Corps show that there was a dialogue between the Corps and its reviewing committee, they do not suggest that any action steps were taken: the committee was not obliged to determine whether or not the Corps' final adjustments to its analysis, or responses to their questions and concerns, adequately resolved the issues raised. This important function of assessing responsiveness and adequacy was assigned to Corps headquarters; in every case, Corps headquarters found that the issue had been resolved. In addition, the reviewers did not make their own evaluation of the merits of the project.

The Corps' conclusion that the project is economically justified is simply not supported by its own analysis. We have focused on six areas that show the weaknesses of the Corps' conclusions.


1. Crude Oil Benefits: There is disagreement between the Corps and the company that performs lightering for crude oil tankers for Philadelphia refineries regarding lightering costs. The Corps has acknowledged that if the lightering company is correct, project benefits are significantly less than project costs. ("Lightering" refers to the process of transferring oil from one vessel to another, so that the first can reduce its sailing draft to the depth of the channel.)

2. Dredge Spoil Disposal: Despite Corps claims to the contrary, the availability of suitable land for disposing of dredged materials resulting from this project is not clear. Moving this material to more distant sites or finding and implementing "beneficial uses" would seriously impact project costs.

3. Discount Rate: The Corps' most recent justification for this project depends on the use of a discount rate that is at a historic low point. If, for example, the Corps used the rate established by the Office of Management for evaluating projects, this project would not be economically justified even if all of the Corps' other current assumptions regarding project costs and benefits remained unchanged.

4. Project Beneficiaries: Clearly, some of the benefits to this project will accrue to non-U.S. entities. Although the Corps is not required to analyze the extent of this incidence, it is certainly relevant within the broader context of appropriate federal policy. Benefits accruing to U.S. firms and consumers will probably not exceed project costs even in the Corps' base case.

5. Outstanding Environmental Issues: The Corps' Reanalysis Report and the associated documents available on the Corps' Web site do not address any of the environmental concerns raised up to this day. Some state permits must still be obtained. And the Corps has failed to take necessary steps to comply with applicable environmental laws, including the Clean Air Act. The potentially large environmental impacts create project uncertainties that have not been adequately incorporated into estimated total costs.

6. Flawed "Independent" Review: The "independent" review process is demonstrably flawed. The independent review panel did not have all information and perspectives regarding the project, and did not have the opportunity to provide its own assessment of the project. In addition, the panel's role was terminated before all of the relevant issues were resolved. In some cases, important questions raised by the independent review panel were not directly addressed-those issues raised by the panel, which resulted in a benefit cost rate less than 1, were dismissed by the Corps as "unrealistic."

Additionally, throughout the process the Corps has decided to derive conclusions that favor dredging from the available facts. The Corps has also selectively accepted or rejected the views of shippers and other affected firms, to maximize the expected project benefits.

In summary, the Corps has been unable to refute the GAO conclusion, or our conclusion, that the Delaware River deepening project is not economically or environmentally justified. Considering that the Army Corps has already spent more than $20 million studying this project, and many serious concerns remain, it is unlikely that any new deepening project for the Delaware River of similar scope can ever be justified.

We recommend that Congress de-authorize the Main Channel Deepening project for the Delaware River rather than wasting any more taxpayer funds to study an inherently flawed proposal.

The economic analyses contained in this report were conducted by Dr. RobertStearns. Dr. Stearns is currently teaching courses in economics and conductingresearch at the University of Maryland's School of Public Affairs. Previously he has served as Deputy Assistant Secretary of the Army (Civil Works) where he worked on a wide variety of Corps of Engineers Civil Works issues. His total federal service covers 20 years as a transportation economist for the Department of Transportation, the Army Corps of Engineers, and the Assistant Secretary of the Army. Previously, he spent 10 years in academia. He received his PhDin Economics from Yale University and his BA in mathematics from Swarthmore College.

Dr. Stearns was Commissioned by the Delaware Riverkeeper Network and the National Wildlife Federation to conduct this economic analysis. Environmental and complimentary information in this report were provided by Maya K. van Rossum, the Delaware Riverkeeper and David Conrad, Water Resource Specialist with the National Wildlife Federation.



For Additional Information:
Delaware Riverkeeper Network
P.O. Box 326
Washington Crossing, PA 18977
215-369-1188

National Wildlife Federation
1400 16th Street N.W., Suite 50
Washington, D.C. 20036
202-797-6697





| Home |  | Contact Us |   | Employment Opportunities |   | Help |   |Site map |

Copyright © 2006, GreenTreks Network, Inc.